COMPLETED PROJECTS

Integrity, Quality, Commitment

EARTHWORKS

Client: Cargill Limited
Location: Camrose, AB 
Completion Date: July 2015
Project Scope: Earthworks, Rail Services, Underground Services, Industrial Maintenance
This project required building and shaping of all plant roads and installation of over 6 km of railbeds for a new Canola Processing Plant, which included the movement of 1,200,000 cubic meters of soil using a GPS system. Excavation of storm drainage ponds, including ditching and culverts. Installation of a storm pond lift station with all required appurtenances including erosion control, site grading and seeding.

Client: Town of Bashaw
Location: Bashaw, AB
Completion Date: September 10, 2021
Project Scope: Earthworks
The scope included supply and installation of Rhinoskin geomembrane, processing onsite waste concrete and placement of liner. Removal of biosolids from anaerobic cells and placement of compacted clay fill. Removal and replacement of 146m of 500mm SDR35 sanitary main. Removal and replacement of 1200mm and 1500mm manholes, site restoration and clean up.

Client: Sturgeon County, AB
Location: Villeneuve Lagoon
Completion Date: October 4, 2021
Project Scope: Earthworks
The project consisted of all earthworks and associated wastewater pumping and management for the construction and rehabilitation of new and existing embankments. Removal and construction of MH control structures inclusive of piping and erosion protection systems. Construction of a sludge dewatering bed, coordination of sludge removal and disposal. Disposal of concrete waste material and concrete rubble. Site restoration and clean-up.

Client: City of Camrose
Location: Wastewater Treatment Plant
Completion Date: Ongoing
Project Scope: Earthworks
The work consists of reconstructing existing storage lagoons, supply and installation of 900mm of forcemain. Supply and installation of overflow/outflow piping and concrete control structures and aeration piping. Construction of new building pad & access road, erosion & sediment controls, and restoration of site conditions/grading. The work also includes removal and disposal of existing yard piping, aeration piping, control structures, and waste materials. The project spans a schedule of 2 years with the majority of the project being completed within the first year. 

Client: City of Wetaskiwin
Location: Wastewater Treatment Plant Facility
Completion Date: Ongoing
Project Scope: Earthworks
The work consists of site grading, excavation and backfill for structures and site development. Lagoon desludging and lagoon clay liner construction. Supply and installation of deep site utilities. Excavation, bedding and backfill for shallow utilities. Gravel road construction. Import and export of suitable and unsuitable earthen materials. Site specific activities to assist project success. 

Mobirise

RAIL SERVICES

Client: CP Rail
Location: Camrose, AB 
Completion Date: July 2015
Project Scope: Rail Services
Construction of the west and east leg of tracks, switch pad and access road. Directional drilling of highway crossings. Supply and installation of six culverts of various sizes, site grading, restoration and cleanup.

Client: South West Terminals 
Location: Antelope, SK 
Completion Date: October, 2019  
Project Scope: Rail Services
This project required the import of 66,000m3 of soil to facilitate the extension of a rail siding for the client. Installation of 450m of culvert ranging from 500mm-1000mm to assist with drainage, procurement and placement of sub-ballast to accommodate rail construction, and the construction of new roads to gain access from the highway. 

Mobirise

INDUSTRIAL CONSTRUCTION & MAINTENANCE

Client: Suncor Energy
Location: Edmonton, AB 
Date: Ongoing
Project Scope: Industrial Construction and Maintenance, Rail Services, Underground Services, Hydro-vac Services
Nu Edge has worked with Suncor Energy in Edmonton since 2013. Utilizing our Multi-Use Agreement, we have been involved in many aspects of maintenance and construction within the refinery. From firewater upgrading and replacement, hydrovac services and snow removal, to berms, crane pads, and grade work/turnout replacements for rail contractors , we are proud to continue our relationship with Suncor.

Client: Cenovus Energy
Location: Cold Lake, AB 
Completion Date: 2012-2013
Project Scope: Industrial Construction and Maintenance, Underground Services, Hydro-vac Services
Nu Edge has completed three different projects for Cenovus Energy. Cooperation and coordination with other contractors, safety personnel, and subcontractors working on site was essential on these jobsites.

Some of the work performed on these projects included:
• Installation of an above ground wastewater treatment plant, supply and installation of service mains and lift station for a 600 man camp, and the installation of a fire water main extension from the operations center to the plant.
• Installation of service mains, lift stations, and force mains for an 800 man camp. Tie-in of service stubs to a 500 man temporary camp located at Cenovus – Silvertip Den camp on the Cold Lake Air Weapons Range.
• Survey and layout of new utilities. Installation of deep utilities and sanitary lift station, including all pumps and control systems, and butt fusion welded sanitary sewer piping. Installation of potable water lines and valves, followed by pressure testing, flushing and disinfection of water lines. Installation of a fire water system, including all piping, valves and hydrant, and pressure and leak test of system. Installation of 100mm “yellow jacket” and 50mm natural gas distribution HDPE butt fusion welded piping and all appurtenances, and pressure and leak test gas line.

Client: PCL Intracon
Location: Joffre, AB 
Completion Date: September 2014
Project Scope: Industrial Construction and Maintenance, Underground Services
Nu Edge was selected by PCL Intracon to complete the site preparation for a new transformer facility. The incredibly tight worksite meant that our employees were operating equipment around up to five other subcontractors at a time. Our team’s commitment to safety ensured that all activities were completed safely, on schedule, and on budget.

Mobirise

UNDERGROUND SERVICES

Client: Samson Cree Nation
Location: Maskwacis, AB 
Completion Date: Ongoing
Project Scope: Underground, Industrial Construction
This involved site preparation for the construction of a new waste transfer station, including clearing and grubbing, excavation and backfill for the installation of culverts and conduits, and the supply and placement of geotextile. Construction of a retaining wall, bin pads, a concrete block wall bunker, as well as a vehicle garage, attendant trailer, and various storage structures.
Working for the general, Aecon, we removed and replaced approximately 1,900 meters of existing sanitary sewer, supplied and installed manholes, service tees, CIPP, and re-rounded three casings and a trunk portion. This job was completed by a combination of open cut method, jack and bore, and HDD, while implementing and maintaining an extensive traffic accommodation strategy.

Client: Town of Daysland
Location: Daysland, AB
Completion Date: Ongoing
Project Scope: Underground Services

The project included the supply and installation of a new sanitary lift station including all process, electrical, control and instrumentation components. Supply and installation of 1,890m of 300mm DR17 sanitary forcemain from the new lift station to the existing lagoon, installation of 86.7m of 660mm steel pipe under a railway crossing by auger bore. Installation of all required fittings, valve replacements and tie-ins to the sanitary system. Removal and replacement of facultative and storage drain valves. Removal and replacement of (6) control structures. Upgrades to the RV dump pad, landscaping, parking pad, site grading and access roads. Site restoration and clean up.  

Client: Town of Provost
Location: Provost, AB
Date: Ongoing
Project Scope: Underground Services
The project includes upgrading the existing main lift station servicing the town of Provost. Installation of additional process mechanical pump, new piping, electrical cabinets, instrumentation equipment, HVAC system and emergency back-up generator. Removal, disposal and salvage of the existing equipment within the lift station. Construction of a new 3,000 meter HDPE sanitary forcemain complete with gate valves, combination air vacuum valves, controls structure at the lagoon. Abandonment of the existing forcemain.

Client: Samson Cree Nation
Location: Maskwacis, AB
Completion Date: Ongoing
Project Scope: Underground Services
The project consisted of the supply and installation of a precast concrete panel booster station building complete with the associated roof and foundation. Supply and install all associated process pipe and equipment, HVAC, plumbing, instrumentation, electrical and programming components within the booster station building. Installation of (2) domestic water pumps, (2) generator sets complete with cast in place concrete pads and electrical programming components. Complete all civil site work at the booster station and WTP. Commissioning of the booster station and all associated components.

Mobirise

City of Edmonton

Client: Clark Builders
Location: Edmonton, AB
Completion Date: 2020
Project Scope: Underground Services
Updated servicing for Fort Edmonton Park. Involving highly detailed excavation through existing utilities, and narrow passages.

Client: Hussaini, JRJ, Gurdawara
Location: Edmonton, AB            
Completion Date: 2022
Project Scope: Underground & Earthwork Services
Multicultural Subdivision Development located in Edmonton. Acted as General Contractor for all civil work including, earthworks, underground, and paving. Completed to City of Edmonton and EPCOR spec.

Client: Spruce Gold Patnership
Location: Spruce Grove, AB
Completion Date: Ongoing
Project Scope: Underground Services
This project involved the installation of 530 meters of 1,200mm diameter gravity sanitary sewer by open trench method at depths ranging from 2 to 8 meters, including 250 meters of trench box work through a residential area. This involved four tie-ins to the existing sanitary main, and site works consisting of clearing, grubbing, stripping with erosion and sediment control, replacement of topsoil and site restoration.

Client: Streetside Developments
Location: Edmonton
Completion Date: 2021
Project Scope: Underground Services
A multi-CRU development located in South Edmonton

Mobirise
Address

4218 43 Street
Camrose, Alberta   T4V 5H4

Contacts

Email: info@necltd.ca 
Phone: 780-679-7825 
Fax: 780-672-8523

Created with ‌

Offline Website Builder